(Summary description)One:Pre-construction Information ;1. Bid-winning notice and construction permit;2. Construction contract ;3. Supervision contract for entrusted supervision project ;4. Construction drawing review approval letter and construction drawing review report ;5. Quality Supervision Registration Form ;6. Key points of quality supervision and quality supervision work plan;7. Geotechnical engineering survey report ;8. Construction drawing review record ;9. The construction organization design or construction plan approved by the supervisor (or the owner) ;10. Commencement report;

The Chairman of Beijing GOWE Holdings Yun Naijian Had an In-depth Conversation with Chairman Chen Honglin on Matters Related to the Prefabricated Construction Industry Entering Our Park

(Summary description)One:Pre-construction Information ;1. Bid-winning notice and construction permit;2. Construction contract ;3. Supervision contract for entrusted supervision project ;4. Construction drawing review approval letter and construction drawing review report ;5. Quality Supervision Registration Form ;6. Key points of quality supervision and quality supervision work plan;7. Geotechnical engineering survey report ;8. Construction drawing review record ;9. The construction organization design or construction plan approved by the supervisor (or the owner) ;10. Commencement report;

  • Categories:Group News
  • Author:
  • Origin:
  • Time of issue:2017-07-10 00:01
  • Views:
Information

One:Pre-construction Information

1. Bid-winning notice and construction permit

2. Construction contract

3. Supervision contract for entrusted supervision project

4. Construction drawing review approval letter and construction drawing review report

5. Quality Supervision Registration Form

6. Key points of quality supervision and quality supervision work plan

7. Geotechnical engineering survey report

8. Construction drawing review record

9. The construction organization design or construction plan approved by the supervisor (or the owner)

10. Commencement report

11. Quality management system registration form

12. Construction site quality management inspection records

13. Technical confession records

14. Measurement location record

Two:Quality Acceptance Data

1. Foundation groove inspection record

2. Quality acceptance report of foundation pile engineering

3. Quality acceptance report of foundation treatment project

4. Engineering quality acceptance report of foundation and foundation division

5. Project quality acceptance report of the main structure segment

6. Special branch project quality acceptance report

7. Line laying acceptance report

8. Quality acceptance records of foundation and foundation divisions and subdivisions, sub-items, and inspection batches included

9. The quality acceptance record of the main structure division and the sub-divisions, sub-items and inspection batches contained in it

10. The quality acceptance record of the decoration division and its sub-divisions, sub-items, and inspection batches

11. Quality acceptance records of roofing divisions and sub-segments, sub-items, and inspection batches

12. Quality acceptance records of water supply, drainage and heating divisions and sub-divisions, sub-items, inspection batches

13. Quality acceptance records of the electrical division and its sub-divisions, sub-items, and inspection batches

14. Quality acceptance records of intelligent divisions and contained sub-divisions, sub-items, and inspection batches

15. Quality acceptance records of the ventilation and air-conditioning division and its subdivisions, sub-items, and inspection batch

16. Quality acceptance records of elevator divisions and sub-divisions, sub-items, and inspection batches included

17. The unit project and its sub-unit project quality completion acceptance record

18. The quality acceptance record of the division (sub-division), sub-item, and inspection lot of outdoor engineering

Three.:Test Data

1. Cement physical performance inspection report

2. Sand and stone inspection report

3. Test report of concrete mix ratio of various strength grades

4. Strength statistics table, evaluation table and test report of concrete specimens

5. Test report of mortar mix ratio of various strength grades

6. Strength statistics table and test report of mortar specimens

7. Brick, stone and block strength test report

8. Steel mechanics and bending performance inspection report and steel welding joint tensile and bending inspection report or steel mechanical connection joint inspection report

9. Re-inspection report of mechanical properties of prestressed tendons, steel wires and steel strands

10. Pile foundation engineering test report

11. Steel structure engineering test report

12. Curtain wall engineering test report

13. Waterproof material test report

14. Test report of exterior doors and windows of metal and plastic (including materials and three characteristics)

15. The pull-out strength test report of exterior wall facing bricks

16. Building (structure) building (structure) lightning protection device acceptance test report

17. Test report of backfill soil density with special requirements or design requirements

18. Other test reports specified in the quality acceptance specification

19. Inspection record of waterproof effect of basement

20. Ground water storage test records with waterproof requirements

21. Record of roof spray test

22. Exhaust (air) duct inspection record

23. Energy saving and heat preservation test records

24. Test records of strength and tightness of pipelines and equipment

25. System cleaning, water filling, water passing, ball passing test records

26. Illumination full load test record

27. Test record of robustness of large lamps

28. Debugging records of electrical equipment

29. Electrical engineering grounding and insulation resistance test records

30. Test records of strength and tightness of refrigeration, air-conditioning, and pipelines

31. Debugging records of refrigeration equipment trial operation

32. Trial operation and debugging records of ventilation and air-conditioning systems

33. Air volume and temperature test record

34. Unpacking inspection record of elevator equipment

35. Elevator load test, safety device inspection record

36. Elevator grounding and insulation resistance test records

37. Elevator trial operation debugging record

38. Trial operation record of intelligent building engineering system

39. Intelligent building engineering system function measurement and equipment debugging records

40. Other measurement, test, inspection, inspection, test, debugging, and trial operation records necessary for engineering safety and functional inspection of the unit (sub-unit)

Four:Materials, Products, Components and Other Certification Materials

1. Cement factory certificate (including 28-day reinforcement report)

2. Ex-factory certificate of bricks and blocks

3. Factory certificate of steel bar, prestressing force, steel wire, steel strand and sleeve

4. Factory certificate for steel piles, concrete precast piles, and prestressed pipe piles

5. Factory certificate of steel structure engineering components and accessories and materials

6. Ex-factory certificate of curtain wall engineering accessories and materials

7. Factory certificate of waterproof material

8. Factory certificate of metal and plastic doors and windows

9. Ex-factory certificate of welding rod and flux

10. Certificate of conformity for prefabricated components and pre-mixed concrete

11. Delivery certificate of water supply and drainage and heating engineering materials

12. Ex-factory certificate of construction electrical engineering materials and equipment

13. Ventilation and air-conditioning engineering materials and equipment delivery certificate

14. Ex-factory certificate of elevator engineering equipment

15. Factory certificate of intelligent building engineering materials and equipment

16. Other certificates required by construction

Five:Construction Process Information

1. Design changes and negotiation records

2. Engineering survey and set-up record

3. Pre-inspection, self-inspection, mutual inspection, and handover inspection records

4. Records of observation and measurement of settlement of buildings (structures)

5. Construction records of new materials, new technologies and new processes

6. Concealed project acceptance record

7. Construction log

8. Concrete opening report

9. Concrete construction records

10. Concrete mix ratio measurement and spot check records

11. Project quality accident report

12. Project quality accidents and accident cause investigation and handling records

13. Project quality rectification notice

14. Notice of partial suspension of construction

15. Project quality rectification report and application for resumption of work

16. Notification of Project Resumption

Six: Information that Should be Added When Necessary

1. Qualification certificate of survey, design, supervision, and construction (including subcontracting) units

2. Changes and replacements of construction, survey, design, supervision, and construction (including color separation) units and their reasons

3. Practicing qualification certificate for practitioners of survey, design, and supervision units

4. The job certificate of the on-site management salesperson and technical workers of various types of work of the construction (including subcontracting) unit

5. Supervision planning or supervision implementation rules approved by the construction unit (owner)

6. The power of attorney or power of attorney for the design representative assigned by the witness unit to the construction site

7. Power of attorney or power of attorney for the design representative assigned by the design unit to the construction site

8. Other

Seven:Completion Data

1. Project completion report of the construction unit

2. Project completion quality evaluation report of the supervision unit

3. Survey documents and implementation inspection report of the survey unit

4. Design document and implementation inspection report of design unit

5. Construction project quality completion acceptance opinion letter or unit (sub-unit) project quality completion acceptance record

6. Notice of rectification of problems in the completion acceptance

7. Opinions on rectification and acceptance of problems in the completion acceptance

8. The notification of the project with the completion acceptance conditions and the notification of reorganization of the completion acceptance

9. Unit (sub-unit) project quality control data verification record (quality assurance data review record)

10. Unit (sub-unit) engineering safety and function inspection data verification and main function spot check records

11. Unit (sub-unit) engineering look and feel quality inspection record (look and feel quality evaluation form)

12. Opinion form signed by users who sell commercial housing or employee-funded housing

13. Engineering quality warranty contract (book)

14. Construction project completion acceptance report (to be filled in by the construction unit)

15. As-built drawing (including intelligent building division)

Eight: Archived Materials For Quality Supervision of Construction Projects

1. Construction project quality supervision registration

2. Review and approval of construction drawings and review report of construction drawings

3. Work plan for unit engineering quality supervision

4. The notice of the construction project quality supervision meeting and the key points of the confession

5. Construction project quality supervision records

6. Construction project quality management system registration form

7. Construction site quality management inspection records

8. Notification of Acceptance Inspection of Foundation and Foundation Pile Engineering Quality Supervision

9. Foundation groove inspection record and foundation pile engineering quality acceptance report

10. Quality inspection records of foundation and pile engineering

11. Foundation treatment measures and foundation treatment project quality acceptance report issued (or approved) by the design unit

12. The notification and acceptance report of the quality supervision and acceptance inspection of the foundation and foundation divisions

13. Engineering quality inspection records of foundation and foundation divisions

14. The main structure division project quality supervision acceptance inspection notice and acceptance report

15. Project quality inspection records of main structural divisions

16. Special part project quality supervision acceptance inspection notice and acceptance report

17. Line laying engineering quality supervision acceptance inspection notice and acceptance report

18. Steel mechanics and bending performance inspection report and steel structure welded joint tensile and bending inspection report

19. Re-inspection report of mechanical properties of prestressed tendons, steel wires and steel strands

20. Cement physical performance inspection report

21. Test report of concrete test piece strength statistics table and evaluation table

22. Assembled or prefabricated component structural performance inspection certificate and construction joints, joints of concrete under construction, test specimen strength test report when fully loaded

23. Test report on compression and impermeability of waterproof concrete and sprayed concrete, and test report of anchor rod anti-pull force test report

24. Foundation strength (bearing capacity) inspection results of various types of foundations and various types of composite foundations in the foundation treatment project

25. Pile foundation test report

26. Mortar strength statistics table and test piece test report

27. Brick, stone and block strength inspection report

28. Test report of harmful substances in construction materials and indoor environment

29. Re-inspection report of waterproof materials (including waterstop strips and joint sealing materials), thermal insulation and sealing materials

30. Re-inspection report of metal and plastic exterior doors and windows (including materials, wind pressure, air permeability, and water permeability)

31. The pull-out strength test report of exterior wall facing bricks

32. Complete machine installation acceptance report for various elevators, escalators, and moving walks installation projects

33. Hidden acceptance, system linkage, system debugging and system installation acceptance records of various equipment installation projects

34. Drilling spot check records of concrete floor slab thickness

35. Project quality accident report

36. The notice of project quality rectification and the notice of partial suspension of construction

37. Project Quality Resumption Opinion and Project Quality Resumption Notice

38. Unit (sub-unit) project quality control data verification record (quality assurance data review record)

39. Unit (sub-unit) engineering safety and function inspection data verification and main function spot check records

40. Unit (sub-unit) engineering look and feel quality inspection record (look and feel quality evaluation form)

41. Project completion report of the construction unit

42. Project completion quality evaluation report of supervision unit

43. Survey documents and implementation inspection reports of survey units

44. Design document and implementation inspection report of design unit

45. Construction project completion acceptance report

46. Notification of Project Completion Acceptance Supervision and Inspection

47. Quality Assurance Data Verification Record

48. Unit (sub-unit) project quality completion acceptance record (project quality completion acceptance opinion)

49. Reorganize the completion acceptance notice

50. Opinions on reinspection of project completion

51. The notice of rectification of problems in the completion acceptance and the acceptance opinion of the rectification of problems

52. Engineering Quality Warranty Contract

53. Project quality supervision report of the unit (sub-unit)

Note: A complete set of data storage and quality supervision station for curtain walls, steel structures and grids